Phase 2
Following completion of Phase 1 construction work, the Charity pursued a programme of further improvements in consultation with subtenants and local community groups. During 2023-24, the Charity has made significant improvements to the site as set out below:
2023
April |
Donations Signboard erected |
May |
Erection of boundary fencing and planting of a willow tunnel |
June |
Installation of four memorial benches with support from the Prince’s Trust volunteers. |
July |
Successful funding bid to secure grant money for a Nature Trail |
October |
Groundwork GM offered to design, fund and project manage creation of a Sensory Garden. |
November |
Planting of sponsored commemorative trees |
2024
January |
Detailed approval of planning application conditions including creation of two swales to improve surface water run-off and drainage |
February |
Construction of Sensory Garden |
March |
Volunteers complete planting of hundreds of flowers and shrubs on the Sensory Garden. |
April |
Planting of sponsored commemorative trees |