Phase 2

Following completion of Phase 1 construction work, the Charity pursued a programme of further improvements in consultation with subtenants and local community groups. During 2023-24, the Charity has made significant improvements to the site as set out below:

2023

April

Donations Signboard erected

May

Erection of boundary fencing and planting of a willow tunnel

June

Installation of four memorial benches with support from the Prince’s Trust volunteers.

July

Successful funding bid to secure grant money for a Nature Trail

October

Groundwork GM offered to design, fund and project manage creation of a Sensory Garden.

November

Planting of sponsored commemorative trees

2024

January

Detailed approval of planning application conditions including creation of two swales to improve surface water run-off and drainage

February

Construction of Sensory Garden

March

Volunteers complete planting of hundreds of flowers and shrubs on the Sensory Garden.

April

Planting of sponsored commemorative trees